|



With a cost-consciousness,
do-it-yourself approach that has become a way of life for many
competitive regional concrete suppliers, Raineri Ready-Mix in
St. Louis, Mo. waged a constant battle with conveyor-belt
carryback, armed with brooms and shovels. Ultimately fed up
with the arduous, wasteful and sometimes risky routine of
manually removing carryback fallout, the plant cautiously agreed
to try a new design of head-pulley pre-cleaner engineered for
simplicity and economy, and found an immediate payoff.
As one division of Raineri Building
Materials, Inc. — a broad-line, family-owned construction
supplier offering everything from concrete delivery and masonry
tools to specialty plasters for medical/dental and artistic uses
— the ready-mix unit serves a three-county area with two
batching plants, one in St. Louis and the other in Eureka, 30
miles west.
At the St. Louis plant, six material
bunkers each hold up to 350 tons of the most frequently
specified crushed stone, alluvial gravel and sands, lined up
over a 265-ft. tunnel conveyor. The tunnel belt carries
batch-required quantities of these materials to an open pit for
transfer onto a 147 ft. incline conveyor, which carries the
materials to the top of the batching plant. A hopper above the
transfer allows front-end loaders to add various specialty
materials such as colored aggregates stored in surge piles
nearby. Both belts, 30" (762mm) wide and troughed at 35
degrees, typically run at about 750 fpm.
“Our sand and aggregates typically contain a little clay and hit
the belts with four to 10 percent moisture, so they can get
pretty sticky,” explains Secretary/Treasurer Chris Raineri.
“Both the tunnel and incline belts were originally installed
with belt cleaners, but their design forced the cleaners to be
positioned where carryback material cleaned off the...
...Continued
in the pages of Twin Plant News, Subscribe Today! |